PROGRESS PAYMENT
david hornby

The valuer may be called upon to value progress payments payable to the builder during the course of construction of the building. This is because standard form building contracts (eg HIA,MBA) require the payment of the VALUE of work completed not cost. Therefore, if progress payments are determined by quantity surveyors or architects they are carried out by those not expert in value. The improvements nay not be the highest and best use.

The amount payable should be determined using the before and after method of valuation and the difference is the progress payment. Materials delivered to the site pending fitting and installation cannot be included in the progress payment as they are not part of the structure, they are not fixtures. The valuer's final certificate of payment is withheld until all relevant authorities, and experts have issued the certificates of compliance and completion.

There are a number of methods by which a builder can claim payment for work completed
but progress payments is the most common and now standard in the main building contracts. Progress payments are usually paid either monthly, at definite stages of construction, or at other intervals depending upon the terms of the building contract.


The following are typical buildings stages used in calculating progress payments:


    

STAGE

PROGRESSIVE %

Deposit 10%

10%

Floor slab 10%

20%

Roof frame 15%

35%

Close up 35%

70%

Fixing/kitchen 15%

85%

Painting 10%

95%

Practical completion 5%

100%






PLAIN

ENGLISH

CONTRACT






%





1 DEPOSIT

5

should not exceed $10000










2 FLOOR SLAB COMPLETE






Footings poured






Stumps, piers or columns complete






Beams & joists compete






Internal & external drainage complete






Electrical, gas & plumbing rough in below floor complete






Floor slab poured







10

15




3 ROOF FRAME COMPLETE






All farmes straightened






Widnows nailed off






Electrical, gas & plumbing rough in completed






Bath installed






Front & back door complete with locks






Eaves, barge, external wall cladding & roof covering is fixed







15

30




4 CLOSE UP COMPLETE






All farmes straightened






Windows nailed off






Electrical, gas & plumbing rough in complete


2nd FIX




Bath installed






Front & back door complete with locks






Eaves, barge, external wall cladding & roof covering is fixed







35

65




5 FIXINGS COMPLETE






All internal architraves, skirtings doors, cupboards & detailed joinery installed






Plasterboard finished, sanded & cornices fixed






Exterior downpipes fitted & penetrations complete






Decks and landings complete







15

80




6 PAINTING COMPLETE






All ceramic tiling installed






PC items installed






Interior & exterior painting completed







15

95




7 PRACTICAL COMPLETION






All interior fitoff items installed incl door furniture, robe rails, abthroom accessories






Electical plumbing & gas fitoff installed






House cleaned internally & externally






Site cleared - excess items removed







5

100










ADELAIDE

BANK











1ST STAGE






Site 2%






Footings 3%






Floors 5%






Brickwork 30%

40%

40%










2ND STAGE






Roof carpentry

10%





Electrics

2%





Roof cover

5%





Plumber

4%





Plaster float

3%





Ceiling

3%





Paster set

2%

70%










3RD STAGE






Fixing 10%






Plumber 4.5%






Tiler 5%






Painter 5%






Electrics 3%






Grano 1.5%






Clean 1%


100%























































See:


















practical completion